Temple, TX facility advances: site flatwork near complete; factory systems, office, and lab reach new milestones.

Construction progress remains steady across our Temple, Texas campus as teams transition from major exterior work into system integration, interior completion, and early-stage equipment preparation. With more than 145 skilled tradespeople on-site each day across 11 partner companies, November marked a shift toward energization, infrastructure upgrades, and readiness activities for upcoming commissioning phases.
This month, sitewide utilities advanced significantly, the factory reached near-full enclosure, and key interior spaces moved closer to handover. Progress also continued across the laboratory and office buildings as permanent power, finishes, and equipment installations advanced. Together, these efforts are laying the foundation for critical work scheduled in December and early 2026.
These milestones reflect measurable advancement toward facility readiness and support the next phase of commissioning and interior completion.

Site development continued across the campus with major utility upgrades and long-term infrastructure improvements. Crews delivered primary water infrastructure to the entire facility and progressed coordinated work with the City of Temple to support future capacity needs.
With the factory structure now enclosed, the focus has shifted toward internal systems and equipment preparation. Electrical distribution advanced as crews pulled primary wire for factory switchgear and transformers and began cabling from switchgear to distribution panels. Concrete crews completed foundational pours supporting upcoming Argon systems, chillers, and pipe racking installations.
Interior progress continued with electrical and plumbing rough-ins reaching near-completion in several zones.

Installation of the 16-ton overhead crane was fully completed in November. Crews finalized all rail alignments and mechanical connections, bringing the crane to operational readiness. This major milestone increases material-handling capability within the factory and supports the movement of heavy equipment required as commissioning activities ramp up.
Full installation of the atomizer is scheduled for early December. November efforts focused on critical preparation including weldments, foundational components, and alignment work to ensure a smooth installation sequence next month.

Significant energization and interior finish progress moved the office areas closer to turnover. With the Oncor transformer energized, teams advanced electrical, plumbing, and finish work throughout the building.
Southwest Office Building
The laboratory entered its final stage of turnover preparation. With the transition to permanent power, casework installation, tie-ins, and equipment commissioning progressed toward departmental readiness.

December will focus on atomizer installation, continued advancement of overhead systems, interior finishes, and final utility integrations across the factory and office buildings. As major infrastructure nears completion, the project is moving steadily toward key commissioning and handover phases.
“I’m proud of how our teams continue to deliver with precision, discipline, and safety. Each milestone, from site utilities to crane installation and atomizer preparation, brings us closer to realizing a world-class operation here in Temple.”
— Jordan Ralph, Chief Operating Officer
Thank you to our employees, construction partners, and community stakeholders for your continued support. Every utility tie-in, interior finish, and equipment-prep milestone strengthens our foundation as we work to build a state-of-the-art superalloy facility that will serve critical industries for decades to come.
